Skip to main content

Urban Land Consolidation Engineering for the 10th park in Chaojhou Township, Pingtung County

  • Date:2013-05-20
The 10th Park(After Consolidation).jpgThe 10th Park(After Consolidation).jpg
(1)Site Location: Chaozhou Township, Pingtung County
(2)Work Area: The land consolidation area is located at Chaozhou Township urban area near the Chaozhou Train Station, including areas located on Datong section of Chaozhou Township, consisting an area of approximately 0.263 hectare. Scope as listed below:
Southeast limit to Chaozhou Township Balong Rd (exclusive)
Border limit to land number 53 east side.
Southwest limit to land number 337, 338-1, 341, 342 of Chaozhou Township Datong section (exclusive)
(3)Construction Budget: over NTD 1,332,000
(4)Tender Awarding Value: NTD 1,182,000
(5)Main work items : Land Grading Engineering, Road Construction, Landscape Engineering, and Miscellaneous Engineering
(6)Construction Sponsor: Pingtung County Government
(7)Construction Contractor: Xin Na Feng Construction
(8)Commencement Date: May 4th, 2012
(9)Completion Date: July 27th, 2012
(10)Handover Date: August 17th 2, 2012