Tainan City Back Wall (17) and Tugou (6) farm path and waterway renewal and improvement work for the farmland rezoned in early days

  • Date:2022-03-08
Suan Tou (10) North Road Consolidation.jpgSuan Tou (10) North Road Consolidation.jpg
Suan Tou (10) North Road - Post-Consolidation Photograph.jpgSuan Tou (10) North Road - Post-Consolidation Photograph.jpg

1. Work location: Houbi District, Tainan City.

2. Scope of works made: Houbi (17): east to the Donghoubi Center Drain, west to Parcel 270-1, Dingzhouliao sub-section, Xizhouliao section, Yanshui District, south to TSC railway, north to the Donghoubi Center Drain; Tugou (6): east to Zhuzijiao, west to Parcel 1169-4, Shangjiadong sub-section, Shangjiadong section, south to South Line 90, and north to Parcel 899-3, Shangjiadong sub-section, Shangjiajie section.

3. Area: 114 hectares

4. Work owner: Tainan City Government.

5. Planning, design and construction supervision entity: LCEB, the Ministry of the Interior.

6. Work description

(1) Farm path: 11, Houbi (17), 2746 meters long in total. Tugou (6): 9, 1806 meters long

(2) Irrigation ditch: 6, Houbi (17), 1626 meters long in total. Tugou (6): 4, 342 meters long

(3) Drainage ditch: 6, Soubi (17), 779 meters long in total. Tugou (6): 4, 1027 meters long

 (4) Structure works: 82

   Houbi (17): 59

    1. Culvert work: 7

    2. Water diversion work: 2

    3. End-of-stream work: 1

    4. Farming deck bridge: 49

 

   Tugou (6): 23

    1. Water diversion work: 1

    2. Guardrail work: 1

    3. Culvert work: 1

    4. Farming deck bridge: 20