Tainan City Datun (3) farm path and waterway renewal and improvement work for the farmland rezoned in early days

  • Date:2022-03-08
Nanbei 2nd Road.jpgNanbei 2nd Road.jpg
Nanbei 3rd Road.jpgNanbei 3rd Road.jpg

1. Work location: Xiaying District and Yanshui District, Tainan City.

2. Scope of works made: east to City Motorway 174, west to Parcel 1491, Litou Section, Yanshui District, south to Madou Drain, and north to Parcel 1484-1, Litou Section, Yanshan District.

3. Area: 118 hectares

4. Work owner: Tainan City Government.

5. Planning, design and construction supervision entity: LCEB, the Ministry of the Interior.

6. Work description

(1) Farm path: 11, 4740 meters long in total.

(2) Irrigation ditch: 1, 460 meters long in total.

(3) Drainage ditch: 11, 4499 meters long in total.

(4) Structure works: 139 in total

    1. Culvert work: 1

    2. Culvert work: 4

    3. Division deck bridge work: 2

    4. Farming deck bridge: 132